| Ownership |
100% |
| Location |
Limpopo province, South Africa, north of Soutpansberg Mountains, 65km southwest of Musina, 80km southeast of Vele Project |
| Infrastructure |
Excellent existing rail (from Musina directly to Matola), road, power (Eskom) and port allocation (Matola Coal terminal) |
| Status |
Project development |
| Life of mine |
16 years |
| Product |
12.6Mtpa run of mine coal yielding 2.3Mtpa hard coking coal and 3.2Mtpa thermal coal for domestic or export markets |
| Reserves |
172.73Mt mineable tonnes in situ |
| Resource |
344.8Mt mineable tonnes in situ |
| Mining method |
Opencast |
| Regulatory status |
Full suite of authorisations |
| New order mining right |
Granted in May 2015 for 20 years |
| Environmental Authorisation |
Granted in August 2013, transferred to Baobab and validity period extended in July 2016 |
| Integrated Water Use Licence |
Granted in January 2016, valid 20 years but currently suspended following an appeal against the licence |